Readysell can charge a initial charge on a meter, no matter what other charges apply for that meter. The worked example below gives you a outline of how to implement an initial charge on a meter.
You would use an initial charge where you want to charged a initial flag fall fee on a meter. Then all other charges.
For a more detailed explanation of the procedure, see: Setting up meter to use Initial Charge field
Warning |
---|
An initial charge applies in addition to all other charges for the meter. It is not a hire charge or a minimum charge. If nothing else, make sure this is the result you want before you proceed. As always try this out in test before using it in live. |
Worked example
We have machine #5 for Acme Pty Ltd. We want to charge them an initial charge of $10 for the colour meter, no mater what other charges are applied for the colour meter that month.
...