It is a good idea to set this up on the Test Database before you attempt to set it up on the live database.
This is because the task that runs to generate the toners , also runs for other modules.

...

  1. Log onto Readysell>Administration>Toner Pools
  2. Click on New
  3. Insert a Name to stand for the Pool (could be the customer, location, toner part or master machine)
  4. Assign the product to the pool. That is the Part that is for that Meter (eg the mono toner part for that machine meter, each pool is for one toner, so if you have multiple toners in the one machine, you will need to create a toner pool for each toner part.)
  5. Insert a Quantity to stand for the Reserved Supplies (ensure reserved supplies is greater than the stock already in the pool)
  6. If you wish to automatically reorder turn the tick on for 'Automatically Reorder' (this will be controlled and ordered when the task runs)

  7. Now on the Meters Tab click on the Insert action button and search for all the same meters and machines that use up this part (eg if its a machine with a mono toner, you select only the machine meters for MONO for all the machines within the pool)

    Expand
    titleShow me


  8. Highlight each of the same meter (eg mono) for each machine for this Toner Pool and click on OK
    Ensure that there is a value in the field of 'Toner Replacement Increase' for each meter. (Readysell can help by running a script to set this for you if you have a lot of machine/meters)

    Expand
    titleShow me


  9. Now you can assign a Primary Machine.
    This is the machine that the sales order will be created against from the task and the spare toners are to be held against.
    This machine meter part in the pool and on the master machine parts tab will have no start and end date but will hold the reserved stock when shipped.

  10. Select the address for this primary machine.

    This is the address where the toners will be delivered to


    Expand
    titleShow me


  11. Once all the meters for the machines have been inserted into this Toner Pool click on Save or Save and Close.
    By setting up the toner pool, the system populates the Toner Pool Name and the Toner Replacement  Increase onto the Machine Meter. You can see this in the Machines>Meter>Supplies>Toner Pool on the Machine Meter.

    Expand
    titleShow me


  12. A Schedule task will run if you have 'Automatically Reorder' turned on for that toner pool. 
    Task Type = Generate Recurring Transactions
  13. The scheduled task will run either automatically or you can run it manually.
    Note: Do not run the task on the live database if you can help it, in case you have other as this task runs for all recurring transactions set to runup in readysell.
  14. To run it manually log onto Readysell>Administration>Tasks
  15. Task Name = Generate Recurring Transactions
  16. Highlight it and click on the Run Task Now action button in the top ribbon
  17. When this task runs whether it be Enabled or Manually, the system will generate a Sales order if a part is required.
  18. When this task runs, the system will generate a Sales order to fulfil the parts required for each toner pool based upon what the reserve supplies quantity is on each toner pool vs the parts already provided and not started (available on the toner pool)
    When the task is finished running you can see in the log entries tab a message if a part was ordered or not and the sales order related.
    If a sales order already exists that has not been shipped and/or invoiced the system may not create another sales order (depends upon the reserve stock vs the available parts) but the task will show you the outstanding sales order number.
  19. Check for Outstanding Sales orders and complete them. Once completed the system will update the 'Quantity Available' on that Meter Pool. 
Expand
titleShow me



Once the sales order is shipped and the shipment is Finalised, the sales shipment is linked to the primary machine listed within each Toner Pool.
It is not until the Sales order is shipped and finalised that the part is populated onto the toner pool machine part tab.

You can manually use the 'Allocate' action button from within the Toner Pool>Machine Parts tab and allocate a toner to each of the machines just the first time around from within the toner pool (that is the initial setup).

Expand

  1. A Schedule task will run if you have 'Automatically Reorder' turned on for that toner pool.
    Task Type = Generate Recurring Transactions
  2. When this task runs whether it be Enabled or Manually, the system will generate a Sales order if a part is required.
  3. Check for Outstanding Sales orders and complete them. Once completed the system will update the 'Quantity Available' on that Meter Pool. 


Building your own worked example of toner tracking for a pool of machines
Note: for each toner part create a toner pool
Always do this on test database for one toner pool

  • Follow the instructions above to ensure that the product part, machines etc are set up prior to setting up the toner pool
  • Create a toner pool/add the product part that stands for the toner eg mono/reserved supplies and select the machine meters
  • Turn the tick on 'Automatically Reorder' on the toner pool
  • Add a toner replacement percentage if there isn't one on the meter itself
  • Assign a primary machine and address
  • Click on Save
  • Manually run the task - Administration>Advanced>Task>Generate Recurring Transaction - click on Run Task
  • A sales order will be Generated if the automatically reorder flag is activated on the toner pool and if a part needs to ordered (that is reserved is greater than available).
  • The number of parts ordered is based upon the Reserve supplies on the toner pool part less any toners parts that don't have a start date. (Reserve Supplies - Quantity Available >0)
    Check the message on the task to see if a sales order was created for that machine and part
  • Go to the Sales Order Module and either Ship and finalise the shipment or just click on Complete to invoice it.
  • Once the shipment is finalised and/or invoiced the system will populate the machine parts that are on the meter pool onto both the tab of 'Machine Parts' on the toner pool and onto the tab 'Parts' for that machine.

    Expand


  • All of the toner parts are first off assigned to the Primary Machine on the toner pool
    Check the field 'Quantity Available' in the header on the toner pool. It should be the sum of the toner parts not including any parts with a start date.
  • Click on the Machine Parts tab in the toner pool, highlight each of the machine machines individually and click on Allocate
  • Select the machines individually just once the first time around and click on Save as you go. The part first time around will be assigned to each of the machine meters within the pool. (initial starting position)
  • Navigate from each of the machine parts from the pool to the machine>Meter>Part Machine>Meter>Part to start the toner tracking
    Manually change the Supply Level on the part to be 99% as though the toner was just inserted into the machine
    Click on Save
    Gradually reduce the supply level to 15%
    Click on Save
    Now increase the supply level to 95% as though the toner has been replaced with a new toner
    The system will set the current toner part with an end date and the grab a toner from the toner pool and set the start date with the high toner level 
  • The quantity available on the toner pool will reduce by this one that has been consumed by the machine.
  • Go back Machines click on the tab 'Parts' and highlight the part that was just shipped
    Click on the action button 'Start' in the detail area to set the start date if a part has not already been started for that meter

    by clicking on the 'Related' action button
  • On the Machine>Parts tab Click on the Start action button to apply the start date to the toner you just allocated the machine to.


    Gradually manually adjust the supply level value on that part by decreasing it on that part that you have manually started and click on save
    Expand
    titleShow me

  • Now manually set in the field 'supply level' =  99% and Save or Save and Close

  • Image Added


  • Manually change the Supply Level on the part to be 99% as though the toner was just inserted into the machine
    Click on Save
    As you are manually decreasing the supply level on the machine part, go back to the toner pool and have a look at the supply level and the toner percentage


    Expand
    titleShow me

    Image Removed

    Image RemovedImage Added



    Gradually reduce the supply level to 15%
    Click on Save

    Now increase the supply level to 95% as though the toner has been replaced with a new toner

  • At one point when the supply level is lower than usual or lower than the value that is set in either 'Toner Replacement Percentage Increase field' or 'Min Supply level' field on that meter, increase the supply type by at least 15% to something like 95% (so that the system thinks that the toner has been replaced) and click on Save. 
    This means that a new toner has been replaced into that machine
  • The system will set an end date on that machine part and fill in a start date on the next available part based upon how many reserved supplies were set onto the toner pool. 
    The system will set the percentage used on the new part to be the percentage on the old part
  • The task will then run again once the Quantity Available <> Quantity reserved in the toner pool for that toner part.
    The system will set the current toner part with an end date and then grab a toner from the toner pool and set the start date with the high toner level 
  • The quantity available on the toner pool will reduce by this one that has been consumed by the machine.