Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
  1. In the navigation pane, go to Print Services then Navigation panel,>Services> Meter Count Runs
  2. Click on button New to create a new meter count run
  3. In the Description field, enter a description for the meter count run
  4. Click on button Extract Meters. The Extract Machines window displays

    Expand
    titleShow me

    Image RemovedImage Added


  5. Select the Meter Count Run Set from the drop-down list
  6. If required, select Meter Count Cycle from the drop-down list
  7. If required enter Machine Filter, you can use the filter to restrict the meter count run to cover only particular machines.
  8. When you have finished, click
  9. Ensure that you enter the right date
  10. When selecting the meter count run set, the linked meter count cycle auto-populates
    If you are counting a machine separately from the count cycle remove the count cycle and insert a machine filter
  11. If you have already counted the meters for this cycle and you wish to only extract a meter count run for Uncounted meters then click on the check box 'uncounted meters only'
  12. Click on OK
  13. Readysell generates a list of machines that require a count for the selected meter count cycle and displays it in the Line Items tab
  14. Verify the extracted meter count data in the meter count run
  15. Generate the batch of emails by clicking on the button Generate Email Batch and then Send Email Batch
  16. Make any required changes when the counts come back checking for count variance of '0' and any negative count variances. Amend the counts if need be
  17. Click on button Save to save the change

...

  1. changes
  2. If the meter count is complete then you are ready to finalise it by clicking on the action button Finalise, otherwise if you are waiting for later reads to come through do not finalise the count run until then.
    When finalising you may be prompted with a Validations/Warnings review 

    Expand

    Image Added

    Image Added


    You can have a number of meter count runs for the same cycle for the same period
    Once you have extracted/checked counts and finalised each of these meter counts runs for the same cycle you can then Charge it.