Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Click on button New
  2. The Count Cycle window appears

    Expand
    titleShow me



  3. Key in the Cycle ID (this is the short code for the cycle)
  4. Key in the Name for the cycle id code
  5. Select whether the Cycle runs:
    1. Every Day
    2. Every Week
    3. Every Fortnight
    4. Every Month
    5. Every Year
  6. The options below will change according to the selection of how often the cycle runs.
    1. Recur Every Day - removes off all options

      Expand
      titleShow me

      Image Added


    2. Recur Every Week - leaves only the option of which Day Of Week you wish it to be run on

      Expand
      titleShow me

      Image Added


    3. Recur Every Fortnight - leaves only the option of which Day of the fortnight to run on

      Expand
      titleShow me

      Image Added


    4. Recur

      Every

      Monthly - leaves options of 'Number of Months'. This is where you specific if you wish to recur every

      2

      3 months etc and the Day Of the Month. This would be classified as a quarterly cycle

      Expand
      titleShow me

      Image Added


    5. Recur Every Year - leaves 2 options.  Which Day of the Month to run on and which Month of the Year to run on.

      Expand
      titleShow me

      Image Added



  7. Click on button Save and Close to to finish creating/modifying a Meter Count Cycle system reference

...